Sump Pit Rehabilitation Works at NEW-NOV & CTH-RFP

01
About the Project

The scope of works includes the following but not limited to:
Pre and Post track alignment Total Station Survey.
Replacement of sump pit components. (Grating, Cat Ladder etc.,)
Installation of temporary rail fasteners and rail footing. (For Additional support to existing rail)
Hacking of track bed. (Section by Section)
Installation of reinforcements with couplers within track bed and sump pit area. (As of PE design)
Installation of reinforcements for electrical connectivity. (Connected by welding with MPI test on welding)
Casting of track bed and sump pit area. (With Suitable Rapid Setting Concrete)